Project: Bovine-RV14A   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Jeff Lawson   -  
Project:   Vans - RV-14A   -   VIEW REPORTS
Total Hours:601.5
Total Flight Time:
Start/Last Date:Jan 28, 2022 - No Finish Date
Engine:Lycoming YIO-390-EXP119 non-cert
Propeller:Hartzell G2YR/N7605W-2X 74 in. dia composite 2-blade
Panel:Dynon Skyview
 
Friendly URL: https://eaabuilderslog.org?s=Bovine-RV14A

Home or Last Project Picture

Mar 01, 2023     Countersinking and dimpling rear spar - (1.5 hours)       Category: Wings
The rear spar of the right wing needed all of the holes in both its upper and lower flanges countersunk or dimpled, depending on whether they were next to the flange of a doubler plate. I also had to ream to final size all of the rivet holes that match up with the attachment fork, and match-drill 6 holes that fork that didn't go through pre-existing rib holes. Finally, two rows of rivets on the attach bracket needed to also be countersunk.

What's next? Some final deburring and scuffing needs to be done on these rear spar parts, then I can prime them.


 